Resurfacing Work Begins Monday on 5 Blocks of U Street NW

by Borderstan.com — May 1, 2013 at 8:00 am 0

"U Street"

U Street resurfacing work begins at 9th Street and runs to 14th Street NW. (Luis Gomez Photos).

The District Department of Transportation (DDOT) will begin repairing and resurfacing U Street NW between 9th and 14th Streets as part of the U Street NW Streetscape Project. Work is scheduled to begin the week of May 6, weather permitting.

The complete resurfacing will take approximately three weeks to finish.

Three-Step Process

  1. Milling away two inches of the old surface from 9th to 14th Street, estimated three days.
  2. Repairing damaged concrete, about 10 days.
  3. Paving the roadway with asphalt from 9th to 14th Street, approximately three days.

DDOT says that after the asphalt has been removed, pedestrians, bicyclists and drivers should use caution in the area; the roadway will be uneven until the new asphalt surface is in place.

For more information about the U Street NW Streetscape Project, visit their website or contact Chinaka A. Young at chinaka.young[AT]volkert.com.

Get an RSS Feed for all Borderstan stories or subscribe to Borderstan’s daily email newsletter.

Leave a Comment

* Required fields

×

Subscribe to our mailing list